How Screening Works

Last updated: November 20, 2026

How site screening works

A Acrelume screen answers one question fast: is this site worth more of your time? It combines the checks that often decide early-stage solar projects: solar resource, grid access, flood risk and eight land and grid checks. Each check is green (clear), amber (to look at) or red (a red flag: a possible deal-breaker). The ratings below are for ground-mount solar, the default; the Screening for menu (rooftop or carport solar, battery storage, data center, EV fleet or truck charging hub, land for a solar lease) changes how some checks count. If a data source does not answer, the check is marked unavailable, never green.

1. Location and project size

You give a location as an address, coordinates or a click on the map. Addresses are converted to coordinates, and every check runs on that exact point. You can also enter an optional project size in MW AC; it changes the grid thresholds (see below).

2. Solar resource

Acrelume loads long-term average irradiance for the point: GHI, DNI and DHI, yearly and by month. In the Americas the data comes from NREL (now the National Laboratory of the Rockies, NLR), in other regions from the EU's PVGIS. A daily GHI of 5 kWh/m² or more scores green (strong); below that the site is compared with operating solar farms in the same state, so a typical Illinois or New York site is green and only a site that is low for its state is amber. Low sunlight alone is never red.

3. Grid access

Acrelume finds the nearest transmission line (100 kV and up) in the HIFLD dataset, whose newest line data is from 2021, and reports its distance and voltage.

  • No project size: up to 5 km green, 5 to 15 km amber, more than 15 km red.
  • Under 5 MW: the transmission line is context only (green up to 5 km, otherwise amber, never red), because small projects usually connect to the distribution grid.
  • 5–20 MW: nearest 100–161 kV line; green up to 3 km, red beyond 15 km.
  • 20–100 MW: nearest 115–230 kV line; green up to 5 km, red beyond 25 km.
  • Over 100 MW: nearest 230 kV or higher line; green up to 10 km, red beyond 40 km.

4. Flood risk

Acrelume checks the point against FEMA's National Flood Hazard Layer. Inside a high-risk zone (A or V zones) is flagged as a possible deal-breaker; outside, it reports the distance to the nearest high-risk zone.

5. Land checks

  • Wetlands (USFWS National Wetlands Inventory): inside a mapped wetland or open water is red; a wetland within 250 m is amber; none within 250 m is green. NWI is mapped from aerial imagery, not a delineation; a delineation decides.
  • Land cover (USGS Annual NLCD, 30 m, 2025; Alaska NLCD 2016): the class at the pin and the mix in a square of about 300 x 300 m. Built-up land, open water or ice is red; lightly developed land, forest or wetland vegetation is amber; farmland, grassland, shrub or barren land is green. Satellite land cover can lag recent construction or clearing.
  • Protected land and critical habitat (USGS PAD-US 4.1, USFWS final and proposed critical habitat): inside GAP 1–2 land (parks, wilderness, refuges), a conservation easement or final critical habitat is red. Public GAP 3–4 land such as BLM land (needs a lease or right-of-way), proposed critical habitat, or strictly protected land within 1 km is amber. Stream critical habitat is not covered and not every easement is mapped.
  • Slope (USGS 3DEP 10 m elevation, a square of about 300 x 300 m around the pin): more than half the area steeper than 15% grade is red; more than 20% steeper than 10% grade is amber; otherwise green.
  • Prime farmland (USDA NRCS SSURGO soils): prime farmland or farmland of statewide importance is amber, because counties and states often scrutinise solar on it. Never red.

6. Grid context

  • Nearest substation (OpenStreetMap within 15 km, plus substations named at the ends of HIFLD lines): green when close for the project size, otherwise amber. Never red. Volunteers map substations, so "not mapped" does not mean there is none.
  • Grid queue (county) (LBNL Queued Up, data through 2025): active solar and storage MW in the county's transmission interconnection queues. Amber only when the county is among the busiest 10% in the US and the project is 20 MW or more. Distribution queues are not covered. Never red.
  • Electric utility (HIFLD Electric Retail Service Territories, 2023 data): name, type and EIA id, with a link to the utility's hosting capacity map for about 18 utilities. Boundaries are approximate. Informational.

7. Verdict and AI first read

The checks combine into one verdict that counts them, for example "No red flags · 2 to look at · 9 clear" or "1 red flag · 1 to look at · 9 clear", and the AI analyst writes a short first read. See Understanding Your Results.

What the screen does not cover

Acrelume is a first screen, not a design or bankable study. It does not check hosting or grid capacity (it only links to utility maps), zoning, parcels or land ownership, distribution lines or interconnection cost, and it does not model panel layout or shading from nearby objects. Before you commit to a site, confirm interconnection capacity with the utility, get a wetland delineation and a flood survey where needed, and run detailed energy modeling (for example PVsyst).